Timeline of Board Action on the Pool
Dec 16, 2024
In this meeting staff provided a comparison of 38M (costing $21M) vs 45M (costing $23M) requested by new board members (to maintain / remodel restroom building) but did not recommend it, and no consensus was reached to shift design to 38M. No action was taken.
https://go.boarddocs.com/ca/laguna/Board.nsf/goto?open&id=DBUQX46B61F8
October 10, 2024
Board of Education approved the 45-Meter Pool Concept and to Proceed with the Next Steps (CEQA and construction doc development) in the Design Process for the Laguna Beach High School Pool Modernization Project.
https://go.boarddocs.com/ca/laguna/Board.nsf/goto?open&id=D9QPRF569275
Motion Carried 5-0
Sep 26, 2024
In this meeting staff provided a comprehensive project update, including the shift from 45M from 50M and reasons why, the broad involvement from design committee and city-school ad hoc committee meeting results. This was an information item workshop and no action was taken.
https://go.boarddocs.com/ca/laguna/Board.nsf/goto?open&id=D93MM85BDF90
March 14, 2024
Board of Education authorized staff to enter into a contract with consulting firms as listed in the board report - Ruhnau Clark, CW Driver, Ultra Systems and MTGL for design services required to complete the project design phase to modernization of the Laguna Beach High School and Community Pool facility in an amount not-to-exceed $1,700,000.
https://go.boarddocs.com/ca/laguna/Board.nsf/goto?open&id=D32MQJ5C5C5E
Motion Carried 4-1 (Perry dissented)
December 14, 2023
Board of Education approved the facilities master plan update which included the 50 meter pool concept to support both City and School District programs. The last page of the report shows the Capital Improvement Fund 4042 accounting.
https://go.boarddocs.com/ca/laguna/Board.nsf/goto?open&id=CY2SYD749856
Motion Carried 4-1 (Perry dissented)